Multiple Choice
Assume that the economy is in a mild recession, and as a result interest rates and money costs generally are relatively low. The WACC for two mutually exclusive projects that are being considered is 8%. Project S has an IRR of 20% while Project L's IRR is 15%. The projects have the same NPV at the 8% current WACC. However, you believe that the economy is about to recover, and money costs and thus your WACC will also increase. You also think that the projects will not be funded until the WACC has increased, and their cash flows will not be affected by the change in economic conditions. Under these conditions, which of the following statements is CORRECT?
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects, even if this means that a competitor might come in and capture this market.
C) You should recommend Project L, because at the new WACC it will have the higher NPV.
D) You should recommend Project S, because at the new WACC it will have the higher NPV.
E) You should recommend Project S because it has the higher IRR and will continue to have the higher IRR even at the new WACC.
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Which of the following statements is CORRECT?<br>A)
Q27: Which of the following statements is CORRECT?<br>A)
Q32: Susmel Inc. is considering a project that
Q33: Simkins Renovations Inc. is considering a project
Q35: Barry Company is considering a project that
Q41: Tesar Chemicals is considering Projects S and
Q42: Projects A and B have identical expected
Q56: A basic rule in capital budgeting is
Q66: One advantage of the payback method for
Q101: Which of the following statements is CORRECT?<br>A)