Multiple Choice
The risk-free rate is 4%, the market rate of return is 14%, and the project's beta is 1.2. Calculate the certainty equivalent cash flow for year-3.
A) $622.04
B) $360.33
C) $401.90
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified