Multiple Choice
When a firm has the opportunity to add a project that will utilize excess factory capacity (that is currently not being used) , which costs should be used to determine if the added project should be undertaken?
A) Opportunity cost
B) Sunk cost
C) Incremental costs
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified