Multiple Choice
A project requires an initial investment of $200,000 and is expected to produce a cash flow before taxes of 120,000 per year for two years. [i.e. cash flows will occur at t = 1 and t =
2]) The corporate tax rate is 30%. The assets will be depreciated using MACRS - 3 year schedule: (t=1, 33%) ; (t = 2: 45%) ; (t = 3: 15%) ; (t = 4: 7%) . The company's tax situation is such that it can make use of all applicable tax shields. The opportunity cost of capital is 11%. Assume that the asset can be sold for book value. Calculate the IRR for the project: (approximately)
A) 12.00%
B) 11.00%
C) 17.73%
D) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Two mutually exclusive projects have the following
Q6: When calculating cash flows, it is important
Q7: A project requires an initial investment of
Q8: Which of the following countries allow firms
Q9: If the discount rate is stated in
Q11: The cost that is incurred as a
Q13: Real cash flow occurring in year-2 is
Q14: Net Working Capital is the:<br>I. short-term assets<br>II.
Q15: If the nominal interest rate is 7.
Q18: Briefly explain how the decision to replace