Multiple Choice
If actual direct material costs are greater than standard direct materials costs, it means that
A) actual costs were calculated incorrectly.
B) the actual unit price of direct materials was greater than the standard unit price of direct materials.
C) the actual unit price of raw materials or the actual quantities of raw materials used was greater than the standard unit price or standard quantities of raw materials expected.
D) the purchasing agent or the production foreman is inefficient.
Correct Answer:

Verified
Correct Answer:
Verified
Q31: The most rigorous of all standards is
Q52: Which of the following is not considered
Q91: When it comes to variances,<br>A)actual costs that
Q92: If standard costs are incorporated into the
Q93: In income statements prepared for management under
Q94: All of the following variances are reported
Q95: If the materials price variance is $600
Q97: A manufacturing company would include setup and
Q98: Wild West Inc.produces a product requiring 3
Q99: A favourable variance that is significant in