Multiple Choice
The standard number of hours that should have been worked for the output attained is 8,000 direct labour hours and the actual number of direct labour hours worked was 8,400.If the direct labour price variance was $8,400 unfavourable, and the standard rate of pay was $18 per direct labour hour, what was the actual rate of pay for direct labour?
A) $17.00 per direct labour hour
B) $15.00 per direct labour hour
C) $19.00 per direct labour hour
D) $18.00 per direct labour hour
Correct Answer:

Verified
Correct Answer:
Verified
Q44: A company uses 3,150 kilograms of materials
Q45: If the standard hours allowed are less
Q46: If a company is concerned with the
Q50: An unfavourable materials quantity variance would occur
Q51: An overhead fixed volume variance is calculated
Q52: Normal standards<br>A)should not be rigorous but attainable.<br>B)do
Q54: The difference between fixed overhead budgeted and
Q76: Ideal standards<br>A) are rigorous but attainable.<br>B) are
Q110: The overhead volume variance relates only to<br>A)
Q161: It is possible that a company's financial