What is a sunk cost?


A) A significant cost that has the potential to "sink" the organization.
B) A cost that has already occurred, but still must be considered in the decision process.
C) A cost that has already occurred and therefore is not relevant in the decision process.
D) A cost that cannot be changed.

Correct Answer: