Multiple Choice
Which of the following statements is false?
A) The overhead volume variance indicates whether plant facilities were used efficiently during the period.
B) The costs that cause the overhead volume variance are usually controllable costs.
C) The overhead volume variance relates solely to fixed costs.
D) The overhead volume variance is favourable if standard hours allowed for output are greater than the standard hours at normal capacity.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: An unfavourable materials quantity variance would occur
Q31: The standard rate of pay is $15
Q42: Allowance for spoilage is part of the
Q71: The fixed overhead spending variance is calculated
Q72: A standard which represents an efficient level
Q94: All of the following variances are reported
Q110: Use the following information for questions <br>Bridgeware
Q110: The overhead volume variance relates only to<br>A)
Q149: A total materials variance is analyzed in
Q217: A variance is the difference between actual