Multiple Choice
Each of the following may cause an unfavourable variable budget variance except
A) higher than expected use of indirect materials.
B) greater than expected use of indirect labour.
C) increases in indirect manufacturing costs.
D) inefficient use of direct labour.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: The starting point for determining the causes
Q30: The total variance is $10,000.The total materials
Q31: The standard rate of pay is $15
Q38: Variance analysis facilitates the principle of "management
Q71: The fixed overhead spending variance is calculated
Q79: Inventories cannot be valued at standard cost
Q82: Budget data are not journalized in cost
Q89: The formula for the materials price variance
Q90: If the standard hours allowed are less
Q94: All of the following variances are reported