Which of the following could cause a debit balance in the direct material price variance accounts?
A) Paying more than the standard price per unit for direct material
B) Paying less than the standard price per unit for direct material
C) Using more than the standard quantity of direct material
D) Using less than the standard quantity of direct material
Correct Answer:

Verified
Correct Answer: