Question 48

Multiple Choice

Use the following information to answer questions

A company expected its annual overhead costs to be $750,000 and machine hours to equal 100,000 hours. Actual overhead was $745,000, and actual machine hours totalled 97,000 hours.

-How much is the company's predetermined overhead rate to the nearest cent, assuming overhead is applied based on machine hours?


A) $7.45
B) $7.50
C) $7.68
D) $7.73

Correct Answer: