Multiple Choice
Which of the following is a method for breaking process into a series of steps in order to eliminate defects and produce near perfect results?
A) Deming's 14 points management.
B) Six Sigma management.
C) Shewhart-Deming cycle.
D) R chart and x̄ chart.
Correct Answer:

Verified
Correct Answer:
Verified