Solved

PERT and CPM

Question 19

Multiple Choice

PERT and CPM


A) are most valuable when a small number of activities must be scheduled.
B) have different features and are not applied to the same situation.
C) do not require a chronological relationship among activities.
D) have been combined to develop a procedure that uses the best of each.