Multiple Choice
PERT and CPM
A) are most valuable when a small number of activities must be scheduled.
B) have different features and are not applied to the same situation.
C) do not require a chronological relationship among activities.
D) have been combined to develop a procedure that uses the best of each.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: When activity times are uncertain,total project time
Q15: The earliest start time rule<br>A)compares the starting
Q16: It is normal for activities on the
Q17: A path through a project network must
Q18: Use the following network of related activities
Q20: In PERT,the activity duration time is equal
Q21: Slack equals<br>A)LF - EF.<br>B)EF - LF.<br>C)EF -
Q22: Constraints in the LP models for crashing
Q23: The earliest start time for an activity
Q24: The earliest start time for an activity