menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Management
  4. Exam
    Exam 9: Project Scheduling: Pertcpm
  5. Question
    The Critical Path
Solved

The Critical Path

Question 57

Question 57

Multiple Choice

The critical path


A) is any path that goes from the starting node to the completion node.
B) is a combination of all paths.
C) is the shortest path.
D) is the longest path.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q38: The variance in the project completion time

Q49: The length of time an activity can

Q49: Activities require time to complete while events

Q50: ​The main difference between CPM and PERT

Q51: Use the following network of related activities

Q52: To calculate an activity's latest finish time,you

Q52: National Oil Company (NATOCO) must plan the

Q54: A project consists of five activities. Naturally

Q56: Which of the following is a general

Q59: Given the following network with activities and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines