When Activity Times Are Uncertain

Question 32

Multiple Choice

When activity times are uncertain,


A) assume they are normally distributed.
B) calculate the expected time, using (a + 4m + b) /6.
C) use the most likely time.
D) calculate the expected time, using (a + m + b) /3.

Correct Answer: