Burkett Company Uses a Standard Cost System The Over- or Underapplied Overhead Was:
A) $50,000 Under
B)

Question 63

Multiple Choice

Burkett Company uses a standard cost system. Indirect costs were budgeted at $200,000 plus $15 per direct labour hour. The overhead rate is based on 10,000 hours. Actual results were:  Standard direct labour hours 9,000 Actual direct labour hours 10,000 Fixed overhead $190,000 Variable overhead $185,000\begin{array} { l r } \text { Standard direct labour hours } & 9,000 \\\text { Actual direct labour hours } & 10,000 \\\text { Fixed overhead } & \$ 190,000 \\\text { Variable overhead } & \$ 185,000\end{array} The over- or underapplied overhead was:


A) $50,000 under
B) $10,000 over
C) $60,000 under
D) $20,000 over