Multiple Choice
Everett, Inc. budgeted $1,488,000 for total overhead. The standard variable overhead rate was $2 per direct labour hour, or $6 per unit, based on an anticipated activity level of 600,000 direct labour hours. During the year 220,000 units were produced. Fixed overhead costs incurred were $300,000. The variable overhead budget variance was $19,800 unfavourable, and the actual variable overhead rate was $2.10 per direct labour hour.
The actual variable overhead costs incurred were:
A) $1,339,800
B) $1,320,000
C) $1,260,000
D) $1,300,200
Correct Answer:

Verified
Correct Answer:
Verified
Q24: For overhead variances, the difference between the
Q25: Identifying the reasons for variances is usually
Q26: The process of calculating variances and analyzing
Q27: How do managers decide which variances are
Q28: The direct materials price variance is often
Q30: The variable overhead spending variance is calculated
Q31: Everett, Inc. budgeted $1,488,000 for total overhead.
Q32: Hogle Mfg. Co. uses a standard
Q33: Mason, Inc. uses a standard costing system.
Q34: White, Inc. produces a chemical product