Multiple Choice
The predetermined overhead rate for Zane Company is $5 comprised of a variable overhead rate of $3 and a fixed rate of $2. The amount of budgeted overhead costs at normal capacity of $150000 was divided by normal capacity of 30000 direct labor hours to arrive at the predetermined overhead rate of $5. Actual overhead for June was $9500 variable and $6050 fixed and standard hours allowed for the product produced in June was 3000 hours. The total overhead variance is
A) $3050 F.
B) $550 F.
C) $550 U.
D) $3050 U.
Correct Answer:

Verified
Correct Answer:
Verified
Q134: Explain the similarities and differences between standards
Q135: The following direct labor data pertain to
Q136: Which is not one of the four
Q137: Dillon has a standard of 1.5 pounds
Q138: If the standard hours allowed are less
Q140: During March Patt Inc. purchases and uses
Q141: The materials price variance is normally caused
Q142: Monster Company produces a product requiring 3
Q143: The balanced scorecard approach<br>A) uses only financial
Q144: A company uses 40000 gallons of materials