Which One of the Following Would Be the Same Total

Question 114

Multiple Choice

Which one of the following would be the same total amount on a flexible budget and a static budget if the activity level is different for the two types of budgets?


A) Direct materials cost
B) Direct labor cost
C) Variable manufacturing overhead
D) Fixed manufacturing overhead