At the high level of activity in November 7000 machine hours were run and power costs were $18000. In April a month of low activity 2000 machine hours were run and power costs amounted to $9000. Using the high-low method the estimated fixed cost element of power costs is


A) $18000.
B) $9000.
C) $5400.
D) $12600.