Which Part of the Project Initiation Document Is Used to Highlight

Question 8

Multiple Choice

Which part of the project initiation document is used to highlight the work content that is to be completed by the end of the project?


A) Project success measures
B) Business success measures
C) Contracting plan
D) Deliverables in scope
E) None of the above