Retainage in the Context of a Project Management Refers To

Question 3

Multiple Choice

Retainage in the context of a project management refers to:


A) A final project payment the customer holds until all final details are complete
B) A final deliverable that the project team withholds until the final payment is received
C) An initial payment made to the organization to retain the service of the project team
D) A firewall to protect project data
E) None of the above