Multiple Choice
Which one of the following would most likely cause an unrealistic budget to result?
A) All levels of management contributed to its development.
B) The budget has been developed in a participative approach.
C) The budget was developed after considerable planning.
D) The budget has been developed in a top-down fashion.
Correct Answer:

Verified