In a Construction Contract,there Is a $1,000 Per Day Estimate

Question 35

Essay

In a construction contract,there is a $1,000 per day estimate of damages for each day that the contract runs over the completion date.The contractor is 30 days late when the job is completed,resulting in a prospective damage award of $30,000.What is this type of clause,and when will it be enforced?

Correct Answer:

verifed

Verified

This type of clause is known as a liquid...