If a Project Has a Salvage Value Greater Than Zero

Question 88

Multiple Choice

If a project has a salvage value greater than zero, the salvage value will


A) have no effect on the net present value.
B) increase the net present value.
C) increase the payback period.
D) decrease the net present value.

Correct Answer: