Which of the following information is needed to develop a make-to-stock production plan?
I. Forecast by time period for the production plan.
II. Opening inventory.
III. Opening backlog of customer orders.
IV. Desired ending inventory.
A) I, II and III
B) I, II and IV
C) 1, III and IV
D) II, III and IV
E) none of the above