Multiple Choice
A customer requests a new order in a period where there is inadequate material available in the available-to-promise (ATP) for that period, and the period is within the planning time fence. Which of the following is the best first course of action to take in such a situation?
A) Increase the master schedule quantity for that period by enough to cover the order
B) Shift the planning time fence inward
C) Tell the customer they cannot have the order in that period
D) Look for additional material in an earlier ATP quantity
Correct Answer:

Verified
Correct Answer:
Verified
Q11: The final assembly schedule (FAS):<br>A) schedules customer
Q12: If there are customer orders the projected
Q13: Given the following data, complete the
Q14: Which of the following statements is best
Q15: The information needed to develop a master
Q17: Which of the following are objectives of
Q18: Which of the following is (are) true
Q19: The time span for which the master
Q20: The MPS is a vital link the
Q21: The portion of inventory or production not