Multiple Choice

Use the following MRP record and your calculations to answer the following two questions. The component has an order quantity of 100, a safety stock of ten, and a lead time of one period. Complete the following MRP record.
 Week 1234 Gross requirements 25802080 Scheduled receipts 100 Projected available 30 Net requirements  Planned order receipt  Planned order release \begin{array} { l l l l l } \text { Week } & 1 & 2 & 3 & 4 \\\text { Gross requirements } & 25 & 80 & 20 & 80 \\\text { Scheduled receipts } & 100 & & & \\\text { Projected available } &30 & & & \\\text { Net requirements } & & & \\\text { Planned order receipt } & & & \\\text { Planned order release } & & &\end{array}

-Complete the above MRP record. Which of the following statements is correct?


A) a planned order for 50 should be released in period two
B) the projected available in period three is 105
C) the projected available in period three is five
D) the planned order release of 100 is in period 3
E) the planned order release of 100 is in period 5