The following two questions use the information in this MRP record. The lead time is 3 weeks.
 Week 12345 Gross requirements 6050607020 Scheduled receipts 100 Projected available 40903040 Net requirements Planned  order receipt Planned  order release 100\begin{array}{llllll}\text { Week } & 1 & 2 & 3 & 4 & 5 \\\text { Gross requirements } & 60 & 50 & 60 & 70 & 20 \\\text { Scheduled receipts } & & 100 & & &\\\text { Projected available }&40&90&30&&40\\\text { Net requirements Planned }\\\text { order receipt Planned }\\\text { order release } \quad100\end{array}
-The net requirement for week four is:


A) 25
B) 30
C) 40
D) 100
E) none of the above