One hundred units of part A are to be processed on a work center. The setup time is 2 hours and the run time per piece is 10 minutes. The total standard time will be:


A) 2 hours 10 minutes
B) 3 hours 40 minutes
C) 10 minutes
D) 1000 minutes
E) 1120 minutes