In a Three-Variance Method of Factory Overhead Analysis, the Variance

Question 74

Multiple Choice

In a three-variance method of factory overhead analysis, the variance that measures the difference between the factory overhead applied and the actual hours worked multiplied by the standard rate is the:


A) Budget variance.
B) Capacity variance.
C) Spending variance.
D) Efficiency variance.

Correct Answer: