Essay
Factory overhead for the Praeger Company has been estimated as follows: Production for the month was 90 percent of the budget, and actual factory overhead totaled $175,000.
Calculate:
a.The predetermined factory overhead rate.
b.The under- or overapplied factory overhead.
Correct Answer: