Essay
Monte Industries has a standard costing system. The following data are available for July:
a. Actual manufacturing overhead cost incurred: $22000
b. Actual machine hours worked: 1600
c. Overhead volume variance: $3600 Unfavorable
d. Total overhead variance: $2000 Unfavorable
e. Overhead is assigned to production on the basis of machine hours
Instructions
Determine the amount of (1) the controllable overhead variance and (2) the overhead applied.
Correct Answer:

Verified
(1) Volume variance plus contr...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q163: The cost of freight-in<br>A) is to be
Q164: A standard differs from a budget because
Q165: Income statements prepared internally for management often
Q166: Setting standard costs is relatively simple because
Q167: An overhead volume variance is calculated as
Q169: Information on Jayhawk's direct labor costs
Q170: The difference between actual quantity of materials
Q171: Edgar Inc. has a materials price standard
Q172: If a company assigns factory labor to
Q173: In Zero Company's income statement they