Exhibit 17-2 in 2016, Omega Construction Began Work on a Contract with Contract

Question 100

Multiple Choice

Exhibit 17-2
In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows: Exhibit 17-2 In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:    -Refer to Exhibit 17-2. Assuming the performance obligation is satisfied over time, what would be the gross profit in 2016? A)  $102,000 B)  $260,000 C)  $255,000 D)  $425,000
-Refer to Exhibit 17-2. Assuming the performance obligation is satisfied over time, what would be the gross profit in 2016?


A) $102,000
B) $260,000
C) $255,000
D) $425,000