Consider the Following PERT/CPM Network with Estimated Times in Weeks

Question 3

Essay

Consider the following PERT/CPM network with estimated times in weeks. The project is scheduled to begin on May 1. Consider the following PERT/CPM network with estimated times in weeks. The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:   ​  a. Give the expected project completion date and the critical path. b. By what date are you 99% sure the project will be completed? The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity: Consider the following PERT/CPM network with estimated times in weeks. The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:   ​  a. Give the expected project completion date and the critical path. b. By what date are you 99% sure the project will be completed?
a.
Give the expected project completion date and the critical path.
b.
By what date are you 99% sure the project will be completed?

Correct Answer:

verifed

Verified

Related Questions