Essay
Consider the following PERT/CPM network with estimated times in weeks. The project is scheduled to begin on May 1. The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.
Give the expected project completion date and the critical path.
b.
By what date are you 99% sure the project will be completed?
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A project network is shown below. Use
Q5: From this schedule of activities, draw the
Q8: Activities following a node<br>A) can begin as
Q9: All activities on a critical path have
Q11: When activity times are uncertain, total project
Q13: When activity times are uncertain,an activity's most
Q28: Arcs in a project network indicate<br>A)completion times.<br>B)precedence
Q31: For an activity with more than one
Q37: The latest finish time for an activity
Q51: Activities K,M,and S immediately follow activity H,and