Multiple Choice
In conducting a feasibility study, operational feasibility refers to whether:
A) A proposed system is attainable given the existing technology
B) A manager can coordinate and control the activities of the systems department
C) An adequate computer site exists for the proposed system
D) The proposed system will produce economic benefits that exceed its costs
E) The system can be used effectively within the operating environment of an organization
Correct Answer:

Verified
Correct Answer:
Verified
Q10: The tasks involved in "systems maintenance" are
Q11: Employee behavioral problems are rarely important in
Q12: Which of these is not a logical
Q13: A "turnkey" computer system is a complete
Q14: In designing an AIS, system developers should
Q16: One goal that outsourcing rarely achieves is
Q17: After successfully implementing a new system, what
Q18: The "slack time" for a PERT activity
Q19: Which of the following is not a