The most time?consuming path in a PERT network is called the:


A) Slack path
B) Completion path
C) Critical path
D) none of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q32: The term "RFP" stands for "relative forthcoming

Q33: The terms "parallel conversion" and "direct conversion"

Q34: Which of the following is least likely

Q35: When developing a new AIS, it is

Q36: Which of these best describes prototyping as

Q38: Which of these individuals is least likely

Q39: A disadvantage of outsourcing is that a

Q40: With the use of this, a company

Q41: Which of these acronyms is not normally

Q42: The purpose of PERT is to coordinate

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines