Multiple Choice
Due to an unusual program error which had never happened before, the accounts receivable updating run did not process three transactions.The error was not noted by the operator because he was busy working on another project.There were control totals for the file which were printed out.An examination of the printout would have disclosed the error.The best control procedure would be:
A) An error message requiring operator response before processing continues
B) Reconciliation of control total by control clerk
C) Internal audit review of console log
D) Label checking by next computer program
Correct Answer:

Verified
Correct Answer:
Verified
Q41: When developing a Business Continuity Plan (BCP),
Q42: Which of the following is not a
Q43: A sales transaction document was coded with
Q44: All controls available for the computerized accounting
Q45: When erroneous data are detected by computer
Q47: In preparing payroll checks, the computer omitted
Q48: Regarding Mobile Device Management (MDM)solutions, which of
Q49: A company uses the account code 669
Q50: MDM software allows an administrator to control
Q51: Testing processing programs with test data is