Solved

Use the Following Information for the Next 4 Questions

Question 123

Multiple Choice

Use the following information for the next 4 questions.
Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded: Use the following information for the next 4 questions. Hogle Mfg. Co. uses a standard costing system. The standard time to produce one unit is 4 hours, and normal production is 3,000 units monthly. Overhead costs were estimated to be $135,000. The standard variable overhead rate is $5 per machine hour. During April the following results were recorded:   -The variable overhead efficiency variance was A)  $8,000 U B)  $4,000U C)  $2,000 U D)  $4,000 F
-The variable overhead efficiency variance was


A) $8,000 U
B) $4,000U
C) $2,000 U
D) $4,000 F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions