Multiple Choice
Use the following information for the next 4 questions.
White, Inc. produces a chemical product whose primary component is purchased on credit and any discounts are always taken. The following material and labor elements make up the costs of the product: Each container of the chemical product contains 5.7 quarts of material. During the process 5% of the material is lost due to waste. Each container of product also requires 1.2 hours of labor. Each day 2 hours are taken for set-up, cleaning, and breaks. Also, the wage rate is $15 per hour and fringes/payroll taxes are 20% of wages. Clients can take a 3% discount if they pay invoices within 10 days; otherwise, the entire invoice amount is due within 30 days. 1 gallon equals 4 quarts.
-The standard quantity of material per finished unit is
A) 6.0 quarts
B) 5.4 quarts
C) 5.7 quarts
D) 5.415 quarts
Correct Answer:

Verified
Correct Answer:
Verified
Q26: The process of calculating variances and analyzing
Q28: The direct materials price variance is often
Q50: Use the following information for the next
Q51: Use the following information for the next
Q51: For overhead variances, the difference between the
Q52: Use the following information for the next
Q53: Use the following information for the next
Q56: Use the following information for the next
Q58: Use the following information for the next
Q88: The cost categories that are measured and