Multiple Choice
How can ABC information be used to manage constrained resources?
A) ABC information cannot be used to manage constrained resources
B) ABC information can help managers identify the best way to relax constraints
C) ABC information can help managers decrease the rate at which products get through the manufacturing process
D) ABC information can help managers justify price increases due to constrained resources
Correct Answer:

Verified
Correct Answer:
Verified