Which of the Following Is Performed First in Setting Up

Question 65

Multiple Choice

Which of the following is performed first in setting up an ABC system?


A) Identify relevant cost objects
B) Assign costs to the costs pools
C) Identify activities that are part of the manufacturing or service delivery process
D) Allocate activity costs to the cost objects

Correct Answer: