An Assembly Task Has a Learning Curve Rate of 93

Question 7

Essay

An assembly task has a learning curve rate of 93% and reaches a steady state after 70 units with 15 man- hours per unit. What is the estimated number of man- hours required to complete the first and the fifth units?

Correct Answer:

verifed

Verified

23.40 man- hours for...