Multiple Choice
OM Construction Company must choose between two types of cranes. Crane A costs
$600,000, will last for 5 years, and will require $60,000 in maintenance each year. Crane B costs $750,000 and will last for seven years and will require $30,000 in maintenance each year. Maintenance costs for cranes A and B are incurred at the end of each year. The appropriate discount rate is 12% per year. Which machine should OM Construction purchase?
A) Crane A as EAC is $226,444
B) Crane B as EAC is $194,336
C) Crane A as the PV is $816,286
D) Cannot be calculated as the revenues for the project are not given
Correct Answer:

Verified
Correct Answer:
Verified
Q41: Given the following data for Project M:
Q42: A capital equipment costing $400,000 today has
Q43: Briefly explain the difference between an equivalent
Q44: Define the term cash flow for a
Q44: A project requires an investment of $900
Q48: Do not forget to include interest and
Q49: The cost of a resource that may
Q50: Two machines, A and B, which perform
Q51: Preferably, cash flows for a project are
Q74: You should replace a machine when the