Multiple Choice
Generally, postaudits for projects are conducted:
I. to identify problems that need fixing
II. to check the accuracy of forecasts
III. to come up with questions that should have been asked before the project was undertaken
A) I only
B) II only
C) I and II only
D) I, II, and III