Multiple Choice
In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B?
A) 101
B) 151
C) 201
D) 251
Correct Answer:

Verified
Correct Answer: