Multiple Choice
__________is the process of using the logic of dependent demand to calculate the quantity and timing of orders for all subassemblies and components that go into and support the production of the end item(s) .
A) Final assembly schedule
B) Materials requirements planning explosion
C) Disaggregation
D) Capacity requirements planning
Correct Answer: