Multiple Choice
A manufacturer of automobile engines is designing a new Kanban system for engine #321. The demand for #321 is 75 parts per day, and the container can hold 8 parts at a time. The total processing and waiting time is 3 days. The manager wants a safety factor ( α ) of 2 or 200 percent. How many Kanbans are required in this system?
A) 85
B) 90
C) 100
D) 115