Multiple Choice
A hinge manufacturing company employs a Kanban system for a component part. The daily demand is 900 hinges. Each container has a waiting time of 0.05 days and a processing time of 0.37 days. The container size is 60 hinges, and the safety factor (α) is 10 percent. Given this data, the number of Kanbans necessary for the system is:
A) less than 4 Kanbans.
B) more than 4 but less than or equal to 8 Kanbans.
C) more than 8 but less than or equal to 12 Kanbans.
D) more than 12 but less than or equal to 16 Kanbans.
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Kanban is a Japanese word that means
Q12: Long setup times enable a manufacturer to
Q13: Which of the following is a similarity
Q14: Drive-in-Style Motors follows a traditional manufacturing system.
Q15: In the context of the 5S principles,
Q17: In the context of lean tools and
Q18: Any activity, material, or operation that does
Q19: A company is using a Kanban system
Q20: _ is one in which employees at
Q21: Which of the following is true of