Multiple Choice
_____ is a scheduling tool that assigns three time estimates for each activity ( optimistic, most probable, and pessimistic) .This technique allows managers to anticipate delays and potential problems and schedule accordingly.
A) A Gantt chart
B) Prioritization
C) Bottleneck elimination
D) Value-stream mapping
E) The program and evaluation review technique
Correct Answer:

Verified
Correct Answer:
Verified